Operators of the Indian Point 2 nuclear power plant had to shut down the plant for the 5th time in 15 months, after water levels in its steam generators suddenly dropped below normal. Repairs began yesterday after the incident which happened shortly after 6:30 yesterday morning.

A faulty unit in the water-supply system is being blamed for the problem. Officials say the breakdown occurred in a building outside the containment dome and there was no release of radioactivity. It's the 2nd malfunction at Indian Point 2 in less than a week.

On Friday, workers discovered a cracked nuclear fuel rod in that reactor's spent-fuel pool which brought a routine inspection to a halt. A spokeswoman for Entergy Nuclear Northeast, which owns the 33-year-old nuclear power plant, said the utility hoped to be back on line today.

Be alert for scams. WNYC never asks for nor accepts money for coverage or interviews. Anyone making such a request does not represent WNYC.

Top Stories

Are Texas, Georgia and South Carolina Swing States Now?

Cab Drivers On Strike in 'Waiting for Lefty'; Anthony Ippolito Plays Stallone in 'I Play Rocky'

Inside New York's bitter Republican civil war after blue wave

Pete Buttigieg on the Democrats’ Sweep of Congress, and Where They Go from Here

YOU ARE ONLINE